FY26 Fee Schedule
Fee Schedule (Effective July 1, 2026)
Table of Contents Links
Click the Applicable Fee Category to Navigate
Water and Reclaimed Water Connection Fees
*See Fee Schedule Definitions Located at Bottom of Page
aSystem Development Fees are referred to as Capital Recovery Fees in the Durham County Sewer Use Ordinance until such time the Ordinance is revised.
Fee Schedule Definitions
Alternative Design Application - Major: A request made for a deviation from the Durham County Design Standards that significantly impacts design, construction, or future maintenance while still meeting the State Minimum Design Guidelines.
Alternative Design Application - Minor: A request made for a deviation from the Durham County Design Standards that does not significantly impact design, construction, or future maintenance while still meeting the State Minimum Design Guidelines.
Annual FOG Maintenance Fee: The Annual FOG Maintenance Fee covers the cost of administration and two required inspections each year. If an additional inspection is required beyond the two required, a FOG Re-Inspection Fee will be charged.
Annual Permit Maintenance Fee: The Annual Permit Maintenance Fee for industrial users will be billed for all permits that are in effect as of July 1st of each year and covers but is not limited to: compliance data review and judgement, inspection fees, and site visits required for permit administration.
As-Built Review Fees: Base review fee shall be paid at time of initial submittal and covers first two reviews, unless otherwise specified. Base fee applies per phase of project plans (i.e. if a 3-phase project is submitted the fee is 3x the base fee). For each additional review beyond two, the re-review fee shall be charged).
Authorization to Construct: The Authorization to Construct fee includes review of all pertinent information and initial inspection but does not include plumbing plan review. Additional fees will apply for plumbing plan review and/or permit modification.
BSL Permit: This is a stand-alone permit issued to industrial users that operates one or more Bio-safety Level Laboratories.
Comment Review Meeting: A meeting held to discuss questions regarding Durham County Utilities plan review comments. Time slots for these meetings will only be held every Thursday between 2 pm and 4 pm. Contact Durham County Utilities Project Management staff to schedule a time. Meeting will be billed at $150 per hour ($150 minimum) and instructions for making payment will be sent at time of meeting confirmation. If fees are not paid a minimum of 24 hours prior to scheduled meeting time, meeting will be canceled.
Construction Drawing Review Fees: Base review fee shall be paid at time of initial submittal and covers first two reviews, unless otherwise specified. Base fee applies per phase of project plans (i.e. if a 3-phase project is submitted the fee is 3x the base fee plus lot fees if lot fees apply). Phasing any type of project after construction drawing approval will result in a base fee charge per phase only. For each additional review beyond two, the re-review shall be charged.
Consumption (in gallons): Consumption is determined using NCDEQ 15A NCAC 02T .0114 (Wastewater Design Flow Rates).
Flow Reporting Permit: This is a stand-alone permit issued to any non-residential user for the purpose of tracking wastewater flow per current sewer capacity.
Initial BSL Permit Application Fee: This fee will be charged to industrial users submitting an initial Industrial User Permit Application. This fee includes review of up to 5 supplemental documents when submitted with the initial Industrial User Permit Application.
Initial Single-Tenant or Multi-Tenant Permit Application Fee: This fee will be charged to industrial users submitting an initial Industrial User Permit Application. This fee includes review of up to 10 supplemental documents when submitted with the initial Industrial User Permit Application.
Multi-Tenant: Any building or site that leases spaces to more than one Industrial User. Multi-Tenant permits will be issued to the building owner/property manager.
Preliminary County Sewer Review Fees: Preliminary County Sewer Review fees will be charged for the review of any site plans and plats located within the Durham County TWWTP Basin. The base review fee covers the first two reviews. For each additional review beyond two, the re-review shall be charged. The Preliminary County Sewer Review fees must be paid in full before site plans will be approved.
Optional Sewer Video Review: A voluntary procedure requesting Durham County to review sewer video prior to 30-days after installation or aggregate base course with first layer of asphalt installed. Comments provided as part of this review are preliminary and are not considered final review. Each project is still required to submit for Sewer Video Inspection 30-days after installation or aggregate base course with first layer of asphalt installed.
Pretreatment Units: Pretreatment units may include but are not limited to pH neutralization systems, sediment traps, and decontamination equipment.
Pump Station (Private) Inspection: Pump Station Inspection is to ensure all major components have been installed as required by NCDEQ. Engineer of Record is responsible to certify the pump station is operational and meets the NCDEQ permit.
Scheduled Inspection Time: Scheduled inspection times are based on established inspection timeframes identified within the online Durham County Utilities inspections portal
Single-Tenant: Any Industrial User that is the sole industrial occupant of a building or site.
Supplemental Documents: Supplemental documents may include but are not limited to biocide worksheets, safety data sheets, special discharge requests, and review of pilot project documents.
Tenant Space: This phrase refers to all possible suites, rooms, or spaces in a multi-tenant facility that may be individually leased to an industrial user.
Variance Request: A request made for a deviation from the Durham County Sewer Use Ordinance.
State Law Compliance
Willdan Financial Services has completed an analysis of Durham County's Sewer System Development Fees (SDF) to comply with North Carolina Session Law 2017-138 (House Bill 436). To review the completed analysis, click here.